Scaffolding was erected in this area on Tuesday, November 25 to allow the structural engineer and contractors safe, working access to this ceiling area. Contractors prepared the area for work by placing plywood on the scaffolding deck and installing plastic sheeting to keep the dust confined to the work area. (Removing plaster and concrete is [...]
Entries from December 2008
December 7, 2008
Update on West Ceiling Area
December 7, 2008
Update on South Ceiling Area
All of the plaster and concrete in danger of falling has been removed. This has revealed extensive deterioration in the concrete slab the serves as the roof/ceiling structure. Over 50% of the bottom surface of this slab (on which the ceiling plaster is applied) has deteriorated. When the plaster was removed the concrete crumbled away [...]
December 3, 2008
More Updates Coming Today
Sorry it has been so quiet on the Building Blog. With the work underway and the Thanksgiving holiday, I have not had time to post. There are some new photos on Flickr (you can access them on this page to the right) and I will be posting several more posts today.
Please check back for more [...]